Agenda Item

6.7 26-094310:00 A.M. - Consideration of Joining Save Lake Pillsbury Coalition Letter to National Energy Dominance Council, Authorizing Supervisors Crandell and Sabatier to Sign, and Authorizing Inclusion of the Board of Supervisors' August 2026 Letter to FERC as an Attachment

   Oppose     Neutral     Support    
10000 of 10000 characters remaining
  • Default_avatar
    ROBERTA MACINTYRE at September 22, 2026 at 2:28pm PDT

    Why Isn’t Lake County a Member of the Sonoma Water Eel-Russian Project Authority?

    Submitted by: Roberta MacIntyre
    September 22, 2026

    Abbreviated Analysis and Assessment (Analysis was shortened to meet the character limitation of the portal. The full analysis will be provided upon request.)
    This assessment distinguishes between the regional benefits of restoring the Eel River and the concentrated impacts borne by Lake County. Scott Dam removal may be environmentally justified, but Lake County’s exclusion from the current project-authority structure creates a governance problem unless the county receives a formal, meaningful role in decisions affecting its residents, roads, fire protection, water resources, economy, and landscape.

    1. Benefits of Decommissioning
    Removing Scott Dam would reopen upper Eel River habitat for protected salmon and steelhead, restore more natural river processes, and eliminate long-term dam-safety risks associated with an aging structure. It could also avoid future costs for seismic upgrades, regulatory compliance, dredging, and dam operations.

    If adequately funded, decommissioning could also support restoration jobs, habitat work, road improvements, cultural-resource protection, public access planning, and a new post-reservoir recreation strategy. These benefits, however, are conditional; they require enforceable funding, measurable standards, and long-term maintenance commitments.

    2. Risks and Costs to Lake County
    Lake Pillsbury is a community, recreational, economic, and firefighting asset. Its loss would permanently change the area’s identity and could affect homes, tourism, ranching, local businesses, property values, county revenues, and demand for public services. Lake County has also identified wildfire protection, water rights, storage, roads, economic development, restoration, and mitigation funding as necessary issues if Scott Dam is removed.

    The county should require an operational wildfire-water plan developed with fire agencies, funded before reservoir loss, tested for drought conditions, and maintained long term. It should also require sediment analysis, water-quality protections, road and haul-route agreements, emergency-access guarantees, service-cost reimbursement, and clear responsibility if predictions prove wrong.

    Environmental review should also recognize that dam removal trades a long-established reservoir ecosystem for a restored river system. That may be the right policy choice, but it must account for wildlife displacement, invasive-species risks, habitat transition, community disruption, and the unequal distribution of benefits and burdens.

    3. Why Lake County May Have Been Excluded
    There are plausible reasons Lake County may not have been included as a full member. If the authority’s purpose is to plan, finance, own, or operate a replacement Eel-to-Russian diversion, membership may have been limited to agencies that receive and pay for diverted water. Lake County may not be a project customer or beneficiary, and it should not be required to assume debt or rate obligations for a facility serving another watershed.

    Joint-powers agencies also commonly align voting power with financial responsibility. Agencies funding the facility may reasonably expect control over engineering, budgets, water-delivery contracts, rates, and allocation of imported water. That rationale supports excluding Lake County from financial and water-allocation decisions—but not from decisions that create or mitigate impacts inside Lake County.

    Exclusion may also reflect political disagreement: Lake County has opposed removal unless major concerns are addressed, while the successor project depends on a post-Potter Valley diversion strategy. But a directly affected jurisdiction should not lose a meaningful voice merely because it challenges the preferred approach.

    4. Why Complete Exclusion Is Not Justified
    Lake County is the host county for Scott Dam, Lake Pillsbury, and many of the most immediate project effects. Its responsibilities include public safety, roads, land use, emergency services, economic development, and protection of residents and property.

    Complete exclusion creates a host-jurisdiction deficit, a benefit-burden imbalance, an information deficit, and an accountability gap. Water beneficiaries should not control choices that impose physical, fiscal, or public-safety impacts on Lake County without Lake County having formal representation.

    The better distinction is not member versus nonmember. It is between financial responsibility for the diversion and decision rights concerning Lake County impacts.

    5. Recommended Lake County Position
    Lake County should not be required to finance or guarantee a Russian River water-supply facility unless it receives a defined benefit.

    However, no project authority should make decisions materially affecting Scott Dam removal, Lake Pillsbury, wildfire protection, sediment, roads, local water resources, restoration, or mitigation without formal Lake County participation.

    The county should seek limited-purpose voting membership for Lake County impacts; a protected host-county seat requiring Lake County approval for decisions imposing physical or fiscal impacts; or, at minimum, ex officio participation paired with a binding host-community and mitigation agreement.

    6. Minimum Conditions for Support or Neutrality
    Before supporting or remaining neutral on decommissioning, Lake County should require enforceable terms for no-net-loss wildfire suppression capability, secured mitigation funding, verified fiscal compensation, road and service-impact reimbursement, sediment and water-quality protections, domestic-water and groundwater safeguards, habitat restoration with measurable success criteria, long-term monitoring, indemnification, insurance or financial assurance, community-transition funding, and formal representation in decisions affecting the county.

    Conclusion
    Scott Dam decommissioning offers credible public benefits, especially fish passage and removal of long-term dam-safety and aging-infrastructure burdens. It also presents serious, locally concentrated risks to Lake County. The decisive policy question is whether Lake County will be protected from becoming the uncompensated host of a project designed in substantial part to benefit other jurisdictions.

    There is a rational basis for excluding Lake County from financial and water-allocation governance if it is neither a customer nor a funding participant. There is no equally persuasive basis for excluding Lake County from decisions that determine or mitigate impacts within Lake County. The defensible solution is limited-purpose representation, not absolute exclusion.