Agenda Item

4.1 22-1008 9:00 A.M. - PUBLIC HEARING - Consideration of Final Recommended Budget for Fiscal Year 2022-23 for the County of Lake and Special Districts Governed by the Board of Supervisors

   Oppose     Neutral     Support    
2500 of 2500 characters remaining
  • Default_avatar
    Julia Carrera about 2 years ago

    Proposed budget pages 288 & 289:
    1."The levees are sound". This is in direct opposition to the Dec. 2021 Feasibility Study finding the clover creek levee "unstable". Please correct.
    2."Routine levee maintenance..." - what specifically is being done for pest and vegetation control only?
    3.Typo: " SAA Streambed Alteration Agreement". It's an LSAA Lake Streambed Alternation Agreement.
    4."Seek and apply for funding opportunities for gravel and vegetation removal...". - Does this include the Middle Creek Diversion Project?
    5."Conduct sediment removal in priority reaches of Clover and Middle Creek" - which are the priority reaches?
    6."Implement Creek Stabilization Project to damaged ..." - What specifically is this and cost?
    7."Conduct gravel repairs to levees" - What exactly is this and cost?
    8.Why no budget for restoring the Middle Creek Diversion Project to it's original flow capacity?
    9.Why no Feasibility Study options to bring the levee system into 100 year storm compliance?